First Release

Year: LVIII.
Zagreb, 03 December 2021
GRAD-2021-1-2/3

ISSN 1334-0557

COMPLETED CONSTRUCTION WORKS AND ORDERS, BUSINESS ENTITIES EMPLOYING 20 OR MORE PERSONS, THIRD QUARTER OF 2021

 

The value of new orders:

- increased by 9.1% in the third quarter of 2021, as compared to the same period of 2020,
- increased by 20.3% in the period from January to September 2021, as compared to the same period of 2020.

The value of construction works done with own workers:

- increased by 12.0% in the third quarter of 2021, as compared to the same period of 2020,
- increased by 16.0% in the period from January to September 2021, as compared to the same period of 2020.

1. INDICES OF CONSTRUCTION WORKS ON TERRITORY OF REPUBLIC OF CROATIA

   Indices
VII – IX 2021
IV – VI 2021
VII – IX 2021
VII – IX 2020
I – IX 2021
I – IX 2020
VII – IX 2021
Ø 2020
Value of new orders 84,2 109,1 120,3 113,2
Value of construction works done with own workers 98,0 112,0 116,0 117,0

2. NEW ORDERS OF CONSTRUCTION WORKS ON TERRITORY OF REPUBLIC OF CROATIA

                                                                                                                  Thousand kuna 

   Value of new orders Value of new orders, by types of constructions
On buildings On civil engineering works
I – IX 2021 19 386 313 9 166 799 10 219 514
       
I – III 2021 6 108 668 2 825 121 3 283 547
IV – VI 2021 7 209 449 3 351 195 3 858 254
VII – IX 2021 6 068 196 2 990 483 3 077 713

3. VALUE OF CONSTRUCTION WORKS DONE AND BUILDING MATERIAL, COMPLETE UNITS AND STRUCTURES AND PROPULSION MATERIAL USED

                                                                                                                                          Thousand kuna

   Value of construction works done Value of building material,
complete units and structures
and propulsion material used
Total Works done with own workers Works done with
sub-contractors
I – IX 2021 22 237 857 16 104 737 6 133 120 4 963 383
         
I – III 2021 6 571 716 4 792 727 1 778 989 1 350 137
IV – VI 2021 7 965 426 5 714 237 2 251 189 1 865 757
VII – IX 2021 7 700 715 5 597 773 2 102 942 1 747 489

4. VALUE OF CONSTRUCTION WORKS DONE WITH OWN WORKERS, BY TYPES OF CONSTRUCTIONS AND WORKS

   Total, thousand kuna Composition of value of construction works done, by types of works, %
Total New constructions Other works1)
VII – IX 2021         
Total 5 597 773 100,0 67,1 32,9
On buildings 2 427 952 43,4 32,9 10,5
On civil engineering works 3 169 821 56,6 34,2 22,4
I – IX 2021         
Total 16 104 737 100,0 66,6 33,4
On buildings 7 192 769 44,7 33,1 11,6
On civil engineering works 8 911 968 55,3 33,5 21,8

1) Reconstructions, maintenance and repair works of existing buildings.

G-1. VALUE OF CONSTRUCTION WORKS DONE WITH OWN WORKERS, BY TYPES OF CONSTRUCTIONS AND WORKS, JANUARY - SEPTEMBER 2021

G-2. COMPOSITION OF VALUE OF CONSTRUCTION WORKS DONE WITH OWN WORKERS, BY TYPES OF CONSTRUCTIONS, JANUARY - SEPTEMBER 2021

 

NOTES ON METHODOLOGY

Sources and methods of data collection

Data on construction presented in this First Release are collected through reporting method by using the Monthly Report on Construction (GRAĐ-21/M form) and the Quarterly Report on Construction (GRAĐ-21/3M form).

Coverage and comparability

The Monthly and the Quarterly Report on construction are collected from business entities (legal entities and tradesmen) and parts thereof employing 20 or more persons classified according to the NKD 2007. (NN, No. 58/07) into section F construction in the Register of Business Entities or the Crafts Register.

Data refer to all construction works (new constructions and reconstructions, maintenance and repair works on existing constructions) done on the territory of the Republic of Croatia.

Constructions and works are classified according to the Classification of Types of Constructions – KVG.

Definitions

The value of construction works is presented in current prices and includes works actually done during the reporting period, irrespective of whether they are paid for or not.

The value of construction works done includes the value of work, building material, complete units and structures, propulsion material and electricity, expenses of construction machinery usage and equipment and other expenses related to the work in question.

The value of construction works done excludes value added tax, purchase costs of the land, project costs, surveying of land and supervising of services.

The value of new orders is the total value of the contracts made in a reference month with ordering parties. An order is considered to be made on the day when a contract is signed between the ordering party and the contractor.

New orders also include works done by constructor on own account and for sale (business premises and dwellings). Referring to constructions on own account and for sale, it is assumed that the order is placed on the day when works have actually started and that the presumed value of works is included.

More detailed notes on methodology of these surveys are published on the web site of the Croatian Bureau of Statistics at www.dzs.hr.

 

Abbreviations        
           
NKD 2007. National Classification of Activities, 2007 version
NN   Narodne novine, official gazette of the Republic of Croatia
             

 

 

Published by the Croatian Bureau of Statistics, Zagreb, Ilica 3, P. O. B. 80
Phone: (+385 1) 4806-111, Fax: (+385 1) 4817-666
Press corner: press@dzs.hr

Persons responsible:
Milenka Primorac Čačić, Director of Business Statistics Directorate
Lidija Brković, Director General

Prepared by:
Srećko Palej and Mirjana Mikulić


USERS ARE KINDLY REQUESTED TO STATE THE SOURCE.


Customer Relations and Data Protection Department

Information and user requests
Phone: (+385 1) 4806-138, 4806-154
E-mail: stat.info@dzs.hr
Fax: (+385 1) 4806-148

Subscription
Phone: (+385 1) 4806-115
E-mail: prodaja@dzs.hr
Fax: (+385 1) 4806-148

Accesibility settings